CHANGE OF ROOF SLOPE 1/12 TO 3/12

Guest User
11/18/2009
I AM WONDERING, IF THIS METAL ROOF IS GOING TO WORK: 1:12 OVER MOST OF THE ROOF WITH THE PITCH CHANGING TO A 3:12 AT THE TOP FIVE FEET. WHICH SORT OF ROOFING MATERIAL DOES THIS REQUIRE- DOES IT HAVE TO BE STANDING SEAMS, WHICH KIND OF WATERPROOFING UNDERNEATH THE METAL?
Todd Miller
Isaiah Industries, Inc.
11/19/2009
The 1:12 area will require a mechanically seamed standing seam. Underlayment will be as required by code or the manufacturer of the roofing.